PA transfer structure KEI1

Former Member
0 Kudos

Hi All,

Scenario : Engineer to order with WBS element as cost object.

In PA transfer structure i have assigned incoming order cost elements to value fields.

These incoming order cost elements are assigned to source cost elements ( for revenues and costs)

Now my question is when will the data be passed to COPA? Is it during creation of sales order , or when results analysis is carried out or when settlem?

I am trying to understand the flow of data to COPA. Please help me.

Regards,

Reddy

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Reddy

KEI1 is configuration to transfer data from FI posting to CO-PA.

You have to use Profit segment to assign the value when posting.

It does not concern Sales order or any SD data.

BR,

WS.

Former Member
0 Kudos

at the time of billing the revenues will flow in to copa from sd through kofk and cost from vprs.

Answers (1)

Answers (1)

Former Member
0 Kudos

COPA values are updated only after the settlement of your sales order (VA88) in your case

Regards

Radha

Former Member
0 Kudos

Hi Radha,

Thanks for the reply.

Can you tell me how we settle the sales order. T codes etc. This will help me in testing.

Regards,

Reddy

Former Member
0 Kudos

After billing, run for result analysis (KKAK ) and then settle sales order (VA88)

Regards

Radha