MR21 Update for BOM materials

Hi Gurus,

This issue is the extension for the issues I posted in this CO Thread.

I have mat A , and B,C,D as the BOM components, C,D are non stock materials like Gas and water which we use in during the process and there is no Costing view for them so I updated the Price for C,D using MR21 and Saved the data and I can see the std cost in the Acct view MM03 for C,D,

But when I do cost roll for A the main part using CK40N , the new price for C, D are not included and it is calculated @ previous cost estiimate for main material,

Do I need to do any thing else after doing MR21 for C,and D ? to include the new cost in to A?

OR do I need to perform any other method for C, D other than MR21?

Paartha

Edited by: Parthu Birampalli on Sep 8, 2008 8:55 PM