MR21 Update for BOM materials

Former Member
0 Kudos

Hi Gurus,

This issue is the extension for the issues I posted in this CO Thread.

I have mat A , and B,C,D as the BOM components, C,D are non stock materials like Gas and water which we use in during the process and there is no Costing view for them so I updated the Price for C,D using MR21 and Saved the data and I can see the std cost in the Acct view MM03 for C,D,

But when I do cost roll for A the main part using CK40N , the new price for C, D are not included and it is calculated @ previous cost estiimate for main material,

Do I need to do any thing else after doing MR21 for C,and D ? to include the new cost in to A?

OR do I need to perform any other method for C, D other than MR21?

Paartha

Edited by: Parthu Birampalli on Sep 8, 2008 8:55 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Please check the valuation variant ( valuation strategy ) attached to costing variant.

Valuation variant is what tells how to pick the cost of material.

Regards,

Reddy

Former Member
0 Kudos

Reddy,

Thats is fine,, Just now Iwas able to figure it out , we need to run "CKMPRPN" T code for the MR21 material, it worked for me,

If possible please tell me various steps in volved after creation of process order in COR1,what steps should I follow to go until TECO an CLOSED,

Paartha