Payment Means with few checks

In incoming payments -> Payment means -> Check - when I have 2 checks the due date for the second check became automatically with the next month. How can I change it to todays date?

In case that I have few checks the Due date will be automatically todays date

Thanks,

Olga

replied

Hi Olga,

The issue seems to be system designed. I was able to reproduce the issue .

This is what online help explains about the field :

Due Date :

The current date is the default date for the first check. Change if necessary.

Hope it helps.

Regards,

Jitin