Hi there,

I am receiving goods against a scheduling agreement. There are several schedule lines due for various dates. Fore one particular qty - 53 PC, there are two entries showing GR happened for both these entries. While only once the GR has actually been done by user. The contradicting factor is, in ME33L - scheduling agreement shows 2 GRs but in MSEG table there is only one entry !!!

How did this happen? If GR has not happened, why is it not showing it as open qty? How to correct this.

Tcodes used - MD04, ME33L

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Check the PO history properly and comapre it with GR quantity in schedule line screen

Answers (1)

Answers (1)

0 Kudos

Answered.

By mistake GR is done as 53 + 47 quantities for schedule line 100