on 09-08-2008 1:27 PM
Hi
I hv created a Raw matl n assigned to wbs element as project stock.
Then i did PO with item catgy Q 2 times (Rs 10 and Rs 20) n MIGO GR with mvt 101 Q n MIGO GI with 221 Q
Its not getting valuated
The MVP in matl master is not getting updated
While issue (GI) acct doc not getting generated
Pls advise the above all to be happen for the project stock.
Regards
Ram
Hi,
I hope that your project is valuated. You can check that in CJ20N, open ur project and check on 'Control data' tab page of project defn under section 'project stock'
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In case of Project Purchases, your MAP will not get affected.
It depends upon the the Account Assignment Category, you select in PO.
If you select "P" then at the time of GR, it will post the Materials received value to expense account and will not affect MAP. And also stock of materials will get consumed immediately in GR.
And if you select "Q" then the time of GR, it will post the Materials received value to stock account and will update stock of material against the Project i.e. Stock will not get consumed immediately in GR. And when you consume this stock that time it will post the GI document with value of project purchased not MAP.
Check Report MBBS for Project Stock Valuation
To check the difference b/w P & Q;
Go to SPRO > MM > Purchasing > Account Assignment > Maintain Account Assignment Categories OR in OME9
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.