on 09-08-2008 12:44 PM
hi,
Could any one explain the detial steps for Stability test in QM with t Codes
Thanks in Advance,
Pls refer the [Link|http://help.sap.com/bp_pharmav1500/Pharma_DE/html/P56_Scen_EN_DE.htm]
Regards,
Shyamal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Shyamal,
But when am selecting Change Testing Schedule in action box for assign the group and counter of inspection task list type Q, System gives error msg. Inspection plan entered is not compitible with the strategy :QSTABI.
Please reply soon am stuck up with this problem.
Thanks,
Vishal
Hi Vishal,
As the message suggest it self
"You can only assign an inspection plan to a testing schedule item for a stability study if the inspection plan uses the same strategy as the testing schedule."
So in the maintenance Plant (the trx code is IP03 / IP10 i think), check the Strategy assignment at "Maintenance Plan additional data"
And check it at the QP03, inspection plan also. I am not able to guide you where exactly it is to be checked for QP03.
Regards,
Shyamal
Edited by: Shyamal Joshi on Sep 9, 2008 11:28 AM
Hey Vishal I think I got the clue.
- Run T Code CWBQM
- Select Current Working Area; set Q_TSK_000000000010
- Go with Basic Selection Criteria
- Here enter the task list type, Group and Counter Number. Then Load Task list
- Now click on the Tab Header General
- And here check in the line item fields, onr them will be the STRATEGY. if the strategy in the Maintenance Plant and Task list are not same, change it either at IP02 or at CWBQM
Best of luck and Regards,
Shyamal
Hi Vishal,
Go to IP02, enter the maintenance plan and follow as i have directed in my previous reply.
So in the maintenance Plant
(the trx code is IP03 (Here you apply IP02 / IP10 i think), check the Strategy assignment at
"Maintenance Plan additional data"
Assign the strategy to the maintenance plan also.
Regards,
Shyamal
Hi Vishal,
I think you would not have assigned the Packages to the Plan / Task list.
So where you have assign the strategy to the Task list through CWBQM follow the below step in addition to that.
- Select the Row in the Grid and Click on TASK LIST in main menu.
- Click Maintenance Package
- Here Operation wise Maintenance Packages needs to be attached.
Regards,
Shyamal
hi,
According to mr.shyamlal joshi instruction which for creation of maintenance package given below
- Select the Row in the Grid and Click on TASK LIST in main menu.
- Click Maintenance Package
- Here Operation wise Maintenance Packages needs to be attached.
i created the operation and as well as assigned the inspection plan to it. But i am not able to assign the maintenance package as it is disbled.
Pls look into this matter accordingly help me out.
with rgds
Harish Ramachandran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
this can be help full to you
http://help.sap.com/saphelp_47x200/helpdata/en/8f/c0be3befaefc75e10000000a114084/frameset.htm
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.