Capacity Planning

Former Member
0 Kudos

Gurus,

If i have entered a capacity in the interval and shifts information of the workcenter then why do i have 0 of available capacity in the CM01 Tcode. I removed the factory calendar that was selected in the workcenter but still no available capacity shows up on week ends...

Any clue of what can be the pb ?

Cheers,

Olivier

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

I solved the pb. Was coming from work center master data. Factory calendar ID was still on so week ends were considered as none working days.

Cheers anyway,

Olivier

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

Please check Work should mark for finite scheduling in capacity screen?

In OPU3 and OPU5 check active tick mark for capacity generation?

Check work center formula and control key?

Please run MRP with lead time scheduling.

To view the over all capacity load of workcenter in plant use CM01,CM50

Regards,

R.Brahmankar

Former Member
0 Kudos

I should make clear that the capacity that does not appear is the one on week ends...

I have 1200 H available capacity per week which is 3 shifts of 8 hours for 10 operators. Plus 2 shifts of 12 hours on week ends i would expect the available capacity to be 1680 H per week. For some reason the week end capacity is not taken into account...

Thanks for your help