Collective requirement in make to stock.

Dear Experts ,

I guess in Make to stock we always get collective requirement no matter what indicator is set in MRP4 (collective indicator )

I have strategy 40 for header material and no strategy for components. Lot size is EX and minimum lot sizes are maintained. Max lot size is blank. Individual/collective indicator on MRP4 is 2.

In MD61, I had entered demand req type VSF with planning period m (month) and D (day) . After MRP run its creating multiple planned orders.

How to combine them?

Neal

Edited by: Neal Gibson on Sep 8, 2008 2:10 PM

Former Member