Hello,

Is there a way that MRP will schedule process orders to a different

Calendar than that of Sales And Distribution.

So that a day may be a holiday for production and a work day

for sales and distribution

Best Regards,

Itzik Eshed

Accepted Solutions (1)

Accepted Solutions (1)

former_member581212
Active Contributor
0 Kudos

hi,

Normally SCAL tcode is used to handle the calanders....

I think you can define all the above in the same....

Regards

Priyanka.P

AWARD IF HELPFULL

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear,

I am not sure, but have a look on this...

First, you will need to set up the planning calendar.

Menu path: Production -> MRP -> Master Data -> Planning Calendar (MD25)

You will then need to use this planning calendar (the one you created) in the material master when planning your raw materials (MRP2 View in 4.6C - Field name : Planning Calendar).

1. When you maintain the planning calendar you will need to enter a valid from date and valid to date.

2. Your periods will also need to be set up and they will be weekly, for example:

From Date : 11/23/2001 To Date : 11/29/2001 (11/23 is a Friday, this is your from date).

Do this for as may weeks as you wish (say weekly for 2 years).

3. When you have set up the planning calendar, you will then need to make some changes to the weekly lot size configuration (WB), or you may need to create a new lot size key if you do not want to Change 'WB'. Essentially, you will need to use the following in the lot size configuration (OMI4) :

No. of Periods : 1

LotSizeProced.: P

LotSize ind : K

Scheduling : 1

By using the above, you are connecting the planning calendar to your lot size key.

Regards,

Syed Hussain.