on 09-08-2008 8:55 AM
Hello,
Is there a way that MRP will schedule process orders to a different
Calendar than that of Sales And Distribution.
So that a day may be a holiday for production and a work day
for sales and distribution
Best Regards,
Itzik Eshed
hi,
Normally SCAL tcode is used to handle the calanders....
I think you can define all the above in the same....
Regards
Priyanka.P
AWARD IF HELPFULL
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
I am not sure, but have a look on this...
First, you will need to set up the planning calendar.
Menu path: Production -> MRP -> Master Data -> Planning Calendar (MD25)
You will then need to use this planning calendar (the one you created) in the material master when planning your raw materials (MRP2 View in 4.6C - Field name : Planning Calendar).
1. When you maintain the planning calendar you will need to enter a valid from date and valid to date.
2. Your periods will also need to be set up and they will be weekly, for example:
From Date : 11/23/2001 To Date : 11/29/2001 (11/23 is a Friday, this is your from date).
Do this for as may weeks as you wish (say weekly for 2 years).
3. When you have set up the planning calendar, you will then need to make some changes to the weekly lot size configuration (WB), or you may need to create a new lot size key if you do not want to Change 'WB'. Essentially, you will need to use the following in the lot size configuration (OMI4) :
No. of Periods : 1
LotSizeProced.: P
LotSize ind : K
Scheduling : 1
By using the above, you are connecting the planning calendar to your lot size key.
Regards,
Syed Hussain.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.