on 09-08-2008 7:15 AM
Dear all,
I have one question.
Can we settle the process order which is partially delivered?
Need your valuable suggestion.
Regards
Nilesh Joshi.
Dear Nilesh, You can change the status of the Process Order to Technically Completed and do variance calculation before settling it. Go to COR2, under the edit menu you can find functions which is having 'technically completed' to select. Trust this answers to your query and helps much in resolving your problem! Regards, Ashok SINGH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thank you very much for your valuable suggestion.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You can calculate the wip for partial delivered orders and the same may be settled to FI WIP ac debit and Change in invetory account will be credited and once complete the order you can reverse the wip and calculate the variances on the process order.
Regards
Madhav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.