Stability Study

Hi,

Am working stability study cycle of QM. My questn, is ...

When am select change testing schedule key in action box and enter group and group counter of inspection plan system gives error msg, 'The inspection plan entered is not compitible with the strategy :QSTABI. I have create inspn. plan with usage 9 & status 4.

Please revert me asap.

Thanks in advance.

Vishal

Former Member
Former Member replied

hi can you check the t-code IP02 plan's strategy is same in t-code cwbqm

and check the inspection point is 200 for QP02 data

-ashok

0 View this answer in context