on 09-08-2008 6:58 AM
Hi,
Am working stability study cycle of QM. My questn, is ...
When am select change testing schedule key in action box and enter group and group counter of inspection plan system gives error msg, 'The inspection plan entered is not compitible with the strategy :QSTABI. I have create inspn. plan with usage 9 & status 4.
Please revert me asap.
Thanks in advance.
Vishal
hi
pl check the startegy enterd in plan and task list are same?
-ashok