query of pm order budget control

Hi experts

I am facing a problem when testing the budget control function of pm order.

I have assigned a budget profile to pm type pm01 and allocated 100 EUR to

the pm order.

then I issue some goods to the pm order. these goods's value exceed 100 EUR.

but the budget function didn't work. the issue post successfully.

then I go to check the pm order budget.

the current budget 100 eur

assigned budget 15238 eur.

can anyone give some suggestion? thank you!

replied

Hi Mark,

As far as i know budget is what you allot seeing your planned cost or estimated cost. It works when you post the actual cost.

You assign budget profile with avialability control [active] and mention the tolerance limits - which states when system should give you information tht budget has exceeded -- you need to mention percentage here .

You budget wil work when you post actuals like when u do confirmation in IW41 or SOS for services or GR is done for non-stock materials etc .Consult even with the FICO team