Hi Frds,

In my IDES system

1. The schedule lines are preparing after two days from the date of sales order for every sales order.But I want to prepare on the same it self bcoz immediately I want to deliver.

For this I have checked the Lead Time in Sales order & Load & Pick times in Shipping Point(OVXD) also. There is enough material in the plant.

2. when I'm trying to create sales order on saturday or sunday it is displaying that no goods are accepted on the specified date.

For this I have changed the days in factory calender in SCAL.

Plz revert back me with new settings which I should check.

Thanks in advance

Regards,

Ram