Hi Gurus,

How to create operation subcontract order? (like the operation painting). I can define this as a operation in OARC.

Regards

Ravi L Patil

Edited by: ravi patil on Sep 8, 2008 7:07 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

kunal_ingale
Active Contributor
0 Kudos

hi

plz refer following SAP doc for the full process

http://help.sap.com/bp_blv1600/V5600/BBLibrary/HTML/150_EN_IN.htm

regards

kunal

award if helpful

Former Member
0 Kudos

Hi Kunal,

Thanks for suggestion.

But some more clarifications:

When i created the Production Order, for external operation PR got generated. But it doesn't change when the rejection are accounted.

And even we cannot change the quantity from PR. it is comming as grey.

One more thning, i need to send these semifinished goods to vendor. How to move the material outside the company as it is very costly product,the trasability should be there?

And also in PR the item category is comming blank. Will this be OK?

Regards

Edited by: ravi patil on Sep 8, 2008 1:57 PM