on 09-07-2008 12:55 PM
Hi Gurus,
I am working on a make to stock scenario. Stategy group used is 40 Planning with final assembly & availability check is set to 02 Individ.requirements.
I have created one sales order with order qty 1000 kg, but delivered qty is 800 kg.
But when I am creating another sales order of same material, system is not carrying out availability check for that material & I am not able to create delivery, eventhough stock is available for that order.
Please give you valuable suggestions.
Thanks in advance.
Regards,
Ajay
Check whether you have open orders for that material. Normally material stock will be reserved (confirmed) for sale orders on first come first serve basis. You can assign/re-assign stocks to a particular sale order by performing back order processing using transaction V_RA.
Regards,
GSL.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Goto VA02, select the first order and assign 'Reason for Rejection'. Now the material blocked for that order will be released.
Thanks,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.