on 09-07-2008 7:01 AM
hi
plz find the problems?
I have created 2 raw materials for that 2 origin groups and 2 overhead key ,these assigned to2 overhead group. these overhead group is assigned to their RAW MATIRIAL MASTER DATA.
Base----
RM1,RM2
Cost element frm origin TO ORIGIN
400000(RM1 cost element) R1(origin grp)
400000(RM2 cost element) R2(origin grp)
1. OVERHEAD RATE:RM1(10%),RM2(10%)
2. OVER HEAD DEPENDENCY: D010(overhead rate /key)
3. CREDIT KEYu2019S:RC1,RC2
IN THE COST SHEET:
10 RM1
20 RM1(O.H.RATE) 10 RC1
30 RM2
40 RM2 30 RC2
I have created separate overhead cost element.
FOR example RM1=100/-,RM2=200/-AND overhead rate:10% on RM1,10%ON RM2
Now overhead calculation is not showing in CK11N. I want overhead calculation separately on each RAW MATIRIAL. PLEASE tell me, where is mistake and how to make?
thank you
nagesh
Dear Nagesh, In the costing sheet rows, you need to taken 30 in both the 'From row' and 'To Row'. Trust this answers to your query and helps much in resolving your problem! Regards, Ashok SINGH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
DId you assign the costing sheet to the costing variant in OKKN?
Please check
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.