overhead wrongly calculated

hi

i am giving the details please find the problems

I have created 2 raw materials for that 2 origin groups. That is

Base----


RM1,RM2

Cost element frm origin TO ORIGIN

400000(RM1 cost element) R1(origin grp)

400000(RM2 cost element) R2(origin grp)

These origin grp are assigned to their RAW MATIRIAL MASTER DATA.

1. OVERHEAD RATE:RM1(10%),RM2(10%)

2. CREDIT KEYu2019S:RC1,RC2

IN THE COST SHEET:

10 RM1

20 RM1(O.H.RATE) 10 RC1

30 RM2

40 RM2 30 RC2

I have created separate overhead cost element.

FOR example RM1=100/-,RM2=200/-AND overhead rate:10% on RM1,10%ON RM2

Now overhead calculation is calculated wrongly in CK11N, how it is RM1=10/-,RM2=30/-HERE is RM2 IS calculated on total(300),not in 200.where is mistake

thnk u

sowmya

Former Member replied

Dear Sowmya, Please take 30 both in From row as well in To row against row 40. Trust this answers to your query and helps much in resolving your problem! Regards, Ashok SINGH