selection of BOM During MRP

Dear All,

I have three alternatives of BOM.The lot size and the validity period for all the boms is same.Now during MRP Run the system only selects the first alternative and plans the depending materials of that BOM.

I want to set the system in such a way that i can able to select any alternative of bom and carry out the MRP Run.

Please help me ..

Regards

Prashant

replied

Hi Prashant,

With same valid From & To Date and Same Lot Size,

In this case system will select first BOM alternative.

If you want to choose a particular BOM then go for production version ,assuming that u r not willing to change the lot size or valid from & to date,then u lock the production versions which you dont want to show to the system before running MRP except the one which u r willing to choose.

We cant choose manually the prod.version during MRP.

Assuming that in MRP4 view of FERT material u have given option 2 in BOM slection method.

The other way is u manitain different lot size and acccordingly the production version will be selected by the system.

I hope it will help you.

Regards,

R.Brahmankar