special procurement key

Former Member
0 Kudos

Hello Guru's

in the inter company PO, lets say the PO is placed by company A to fetch the material from company B and from specific plant ( 3 ) ....my question is ..can we use " special procurement Key" in the material master to get the standard price from company B, Plant 3 and can we have some percentage in company A, Plant 05 ..how we can config this scenario or is there any best way to do this ........plzz suggest me with details

Thank You

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear,

The special procurement key is used to precisely define how in-house production and external procurement is to be carried out.

The following methods of special procurement are available for in-house production:

Phantom assemblies

Production in alternative plant

Withdrawal from an alternative plant

Direct production

The following methods of special procurement are available for external procurement:

Consignment

Subcontracting

Stock transfer

In your case mentioned:

COMPANY A raising Purchase order for COMPANY B - PLANT 03

You want get material master standard price from COMPANY B - PLANT 03

And regarding percentage of COMPANY A - plant 5 is some incentive/commission on order is you are talking,

Create an Purchase info record in COMPANY A - PLANT 5 combination of Material, Company B (create as a vendor in Company A). Maintain the conditions accordingly, including percentage.

Regards,

Syed Hussain.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Price depends on the Material Master maintained in Each company A (or) B. it does not depend on Special Procurement Key.

If you are doing STO from Plant A to B then in both the plant you have to maintaint the Price control same either V or S

G.Ganesh Kumar