Hi Guys,

Need some help on the integration between PS and PM. It would be really great if you could explain this with a suitable scenario or an example. How will entering the WBS element when creating the Functional Location or the Equipment would reflect in PS.

Please reply ASAP.

Cheerio,

Sbk

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos
Former Member
0 Kudos

Hi Venkat,

your question is not clear..

ok

1.Each eqpt /f.loc which you create in PM can be individually assigned to a WBS .

2.You can create a MO and assign tht to WBS this would add to the planned cost of the WBS .

3. You can settle a MO to a WBS and this would go to the actual cost of WBS .

Regards

pushpa