settling the WBS element costs to an AuC

Please Explain the procedure for settling the WBS element costs to an AuC & then to asset?

replied

Hi,

Please follow the below sequence of steps for this:

1) For WBS element where the asset has to be created, AUC willbe created automatically when the WBS element is in release status to get this investment profile should be assigned to WBS element in Control Tab

2) You can see in the system status show as AUC to see the AUC number follow the path

EDIT-> WBS element -


> Investment program--> Asset under Construction where you can see the AUC which is created automatically

3) Once the above two steps are through, for settlement to AuC goto transaction CJ88 give the WBS element number select the processing type as partial captalization and execute all the costs pertaining to that. WBS elements will be automatically settled to the AUC which is created for that WBS element

Thanks,