V3 Collective Run Cancelled

Former Member
0 Kudos

Hi,

I have enhanced the extractsturcture and moved the Datadource to Production. After the Datasource has been moved. The V3 jobs are getting cancelled.

I could not able to figure out the actual cause of the problem

I did not clean the Delta Queue and I did not stop the V3 job before transporting. Please let me know is there any way to resolve the issue.

I am worried that the we looase deltas. Please help in this regard.

Job Log:

Date Time Message

05.09.2008 14:37:18 Job started

05.09.2008 14:37:18 Step 001 started (program RMBWV311, variant , user name Z57009)

05.09.2008 14:37:18 Queue processing started (MCEX11, 1.000, , 0)

05.09.2008 14:37:19 Extraction queue processing started MCEX11 with 10.306 LUWs

05.09.2008 14:37:36 ABAP/4 processor: MESSAGE_TYPE_X

05.09.2008 14:37:36 Job cancelled

Regards,

Reddy

Accepted Solutions (0)

Answers (2)

Answers (2)

Private_Member_101989
Contributor
0 Kudos

Hello,

It depends on your implementation. But unfortunately the better way to solve that is to initialize that area.

Regards,

Jorge Diogo

Former Member
0 Kudos

Hi Raghav,

Go through this link, it talks about similar issue,

http://vinaysapbw.blogspot.com/2007/07/how-to-retain-deltas-when-you-change-lo.html

Thanks