MRP Procurement proposal

Former Member
0 Kudos

Hi,

I have an issue in MRP result for a one plant.

MRP is creating a planned order for the material(For inhouse production E) eventhough there is sufficient stock to meet the PIR and on the wrong date (I mean: where sufficient stock is available)

If the Procurement type is change to F(External procurement) then the procurement proposal is getting created on the appropriate date (exactly on the shortage)

Please provide your suggestions is there any plant level settings that is influencing this behavior.

Thanks and regards,

Nataraj

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks.

former_member335796
Active Contributor
0 Kudos

Hi,

Check with the Pegging report (Pegged Requirements) in MD04.

The Planned Order may be created to replinish for other date.

Regards,

Siva

Former Member
0 Kudos

Hi Siva,

Thanks for your reply. I verified the pegged requirements. All the requirements for the given order lies on later dates. It is still not known why the planned order is created on a earlier date.

Please provide your valuable suggestions.

Thanks and regards,

Nataraj

Former Member
0 Kudos

Any Plant level settings causing this issue???

Regards,

Nataraj

Former Member
0 Kudos

Hi Natrajan,

Check if any in-house production time is maintained in the material master.

If In-house time is maintained then there is a possibility of creation of planned order earlier.

Also check the scheduling key you are using for the MRP run whether it is 1 or 2. Incase of 2 system will do lead time scheduling.

Thanks N Regards,

Hitendra R Dwivedi