Hi!

When we select the Plant & Business Area in CJ20N while creating the project , the relevant Factory Calendar to the Plant selected should appear by default. Is it possible to do so?

MRD

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi ,

It is not possible to automatically put such field value.I tried with Substitutions but not feasible.u can use standard templates with predefined fields for plant and factory calender.

Rgds

virendra_pal
Active Contributor
0 Kudos

factory calendar should come from scheduling data in the project profile planning board tab default value for factory calendar