cancel
Showing results for 
Search instead for 
Did you mean: 

Is it possibility for BOM

Former Member
0 Kudos

Hi,

One BOM for different material means BOM is same for different FERT material any option for this without creating the separte BOM for every FERT material.

Thanks

shiv

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks

Former Member
0 Kudos

Yes, it cam be done.

When you create a production/process order system will ask for the BOm since it is not available and it asks for referenec material BOM...that time you can enter the referenec material and create production/process order with out actually creatong a BOM. But this will not help in planning, for which you need to go for refrenec material with planning stg 60.

please come back what is your purpose of not creating BOM?

Former Member
0 Kudos

Hi,

Look my requirement is like that suppose A,B,C,D are the FERT material all are useing only one material in BOM that is "F" i want to know that is there any option that create single BOM which has the material "F" & use this BOM always for A,B,C,D

actually i not sure its possiable or not

Thanks

shiv

former_member335796
Active Contributor
0 Kudos

Hi,

this can be handled in Variant BOM.

If several similar products are manufactured whose parts only differ in minor ways,

you can represent these various products using a variant BOM.

Refer below link for further understanding..

[Variant BOM|http://help.sap.com/saphelp_erp60_sp/helpdata/en/ea/e9b8fc4c7211d189520000e829fbbd/content.htm]

Hope this helps..

Regards,

Siva