Earlier in production client,
abs entitlements were calculated as 6 day week
recently its changed to 5 day week automatically, how?
Ex: jan 1 (mon) to jan 7 (sun)
system calculates (EARLIER)
jan 1 to jan 6 = qualifying days
jan 7 to jan 7 = non qualifying day
system calculate (NOW)
jan 1 to jan 5 = qualifying days
jan 6 to jan 7 = non qualifying days