Hi,

How enable modification of PR qty, until PO is made against the PR. After making PO as per PR qty -- in PR, quantity should not be amendable

( i,e if suppose PR qty is 100Nos --> PO created for 100Nos with reference to PR --> after PO release, system should not allow to amend PR quantity as 50Nos).

Please help

Thanks in advance.

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member192897
Active Contributor
0 Kudos

Go to OME0 and Set the Message Numbers 06 608 & 06 648 as Error Messages Such that If any User Tries to Change the PR Quantity will Get an error Message.

Regards,

Ashok

pankaj_singh9
Active Contributor
0 Kudos

Hi,

You can control this by Message Control configuration in following path;

SPRO > MM > Purchasing > Environment Data > Define Attributes of System Messages > System messages > Here maintain following messages as Error Message;

06 648 Requisition quantity already ordered in full (see follow-on docs.) - This will prevent user to reduce the PR Quantity

06 608 Requisition already converted into purchase order & & - This will prevent user to increase the PR Quantity

Former Member
0 Kudos

Thanks a lot. Issue has been resolved.

Former Member
0 Kudos

Activate message as an error or warning for version 00, area 06, message number 608 in OME0 or SAP>> MM> Purchaing> Environment data >>Define Attributes of System Messages >> system messages