Hi,
How enable modification of PR qty, until PO is made against the PR. After making PO as per PR qty -- in PR, quantity should not be amendable
( i,e if suppose PR qty is 100Nos --> PO created for 100Nos with reference to PR --> after PO release, system should not allow to amend PR quantity as 50Nos).
Please help
Thanks in advance.
Go to OME0 and Set the Message Numbers 06 608 & 06 648 as Error Messages Such that If any User Tries to Change the PR Quantity will Get an error Message.
Regards,
Ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can control this by Message Control configuration in following path;
SPRO > MM > Purchasing > Environment Data > Define Attributes of System Messages > System messages > Here maintain following messages as Error Message;
06 648 Requisition quantity already ordered in full (see follow-on docs.) - This will prevent user to reduce the PR Quantity
06 608 Requisition already converted into purchase order & & - This will prevent user to increase the PR Quantity
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Activate message as an error or warning for version 00, area 06, message number 608 in OME0 or SAP>> MM> Purchaing> Environment data >>Define Attributes of System Messages >> system messages
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.