on 09-05-2008 12:24 PM
hi ,
My cliant demands for only one PR to be generated while carrying our MRP run at MD51(WBS element base).
So advise me the steps need to be followed.
Chaya
Hi
In material master MRP4 view set collective indicator and run MD02. It will give one PR but w/o WBS assignment.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please try this Use T code OPUV (Specify Parameters for Network Type) and check the indicator 'CollctveRequstn'
Now,is it possible to generate only 1 PR for all Activities at either Network or WBS Element Level from CJ20N itself.
Regards,
R.Brahmankar