Hello,
I've run MRP without problems, but now I have a problem with one material. It is strange because if I copy that material with MM01, create the BOM and the run the MRP, everything works fine with the new material, but not with the old one.
Any idea why it could be not working, while the copy works perfectly?
It has probably no planning file entry.
This happens from time to time, can especially happen for materials after a migration.
There are several OSS notes about that.
Just check in MD21 is you hav a planning file entry, if no create one individually with MD21 or en mass with MDAB.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
First of all check have u maintained MRP parameters correctly
( MRP type etc.)
Though u have created BOM but if parent material has no requirement then it will not create any requirement for ur created material so check whether parent material is applicable for MRP or Not
Vishal...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You have to check from every point of view as in the case you have to check the type of MRP,LSP,planning file entries,strategy type,avilability check and so on...
Please do the needful and check also the deletion indicator if possible.
Reg,
Deepak.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.