Hello Everybody,

Can we change BOM in Production order (DLV Status) as, because of wrong BOM, Material consumption is wrongly posted.

or i have to make reversal of the difference quantity of wrongly posted material with reference to that production order.

Thanks and Regards

AM

Former Member
Former Member replied

Hi AM,

There is 2 option ,

- Correct Production order with Required BOM

- Correct only Wrong GI done.

For First option ,

You have to reverse all the transections like Confirmations , Goods Movement etc.Its quite difficult but to reassgin the required BOM you have to it.After reverse all the transection do "Read Master Data".It will change the order status to CRTD.Now you can change the BOM.

For Second option ,

Cancel the Material Document through MBST or incase of Auto GI cancel that confirmation.Then do GI for the correct component thorugh MB1A, MIGO or CO11N/CORN.

Regards,

Dhaval