09-05-2008 10:40 AM
Hello all,
if I select my interval for company code largely, the program (RFITEMAP) is very slow. What I can make in this report, so that preformance becomes better.
Example: ( selection criterion )
company code : 1 to 200 -
> very slow
company code: 1 ---> normal
Edited by: Heidi Heinzberger on Sep 5, 2008 11:40 AM
09-05-2008 10:42 AM
Since it's an SAP standard report, you should search in Support Portal for existing notes, or open a new call there describing the problem.
Thomas
P.S. have look at note [1135916|https://websmp130.sap-ag.de/sap(bD1kZSZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1135916]
09-05-2008 10:48 AM
09-05-2008 10:59 AM
Now that would have been a nice slice of information the first time around
Depends on how much you have changed in your Z-copy. The mentioned note might still apply, if only minor changes.
Copying standard Programs to Z-copies is a bad idea by the way. I know it happens all the time all over the world, but there is many follow-on problems during upgrades or patch level changes.
Thomas
09-08-2008 12:39 PM
Hello Thomas,
Thanks for your anwers. I have still another question.
Which code can i use instead of this code ( move-corresponding bsik to wa_pos.). thus the program runs faster ?
Regards
Heidi
Edited by: Heidi Heinzberger on Sep 8, 2008 1:45 PM
09-08-2008 12:48 PM
Please open new threads for new questions, and close the old ones (mark as "answered").
Cheers
Thomas
P.S. there is nothing to be optimized in the given statement