Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Funds Management - budget report (Funds transfers between cost centers)

Good day,

we are using version 4.6C and busy upgrading to ECC 6, one of my colleagues would like to draw a report that shows him the Funds transfers that have taken place within a specific fiscal year, that shows the cost centers and the amounts that have been transferred.

can anyone suggest a transaction that would be suitable, as he want to present it to mngt.

Thank you in advance

Edited by: Admire Hlabane on Sep 5, 2008 11:41 AM

replied

Hi,

Cost centres are not part of FM entities. Did you mean fund centres? For former budgeting (I guess, that it what you are using) you can run FMRP_RFFMEP1BX report.

Regards,

Eli

0 View this answer in context
Not what you were looking for? View more on this topic or Ask a question