Issue with transportation lane validity

Hello,

We are currently having a scenario wherein a HUB is sourcing from two locations. The validity of the transportation lanes is as follows:

Plant1 --> HUB: 1st Jan 2008 to 31st October 2008

Plant 2 --> HUB: 1st November 2008 to 31st December 2008

The transportation lead time from both the plants to the HUB is 2 days.

I have a forecast requirement on 1st November at the HUB. When I run SNP heuristics at the HUB, the system creates a receipt on 30th October with the sourcing location as Plant 2. The start and the end dates of the order are seen as 30th October 2008. The lead time is not respected in this case

Our expectation was that the system should show the start date as 30th October and the end date as 1st November 2008.

has anyone come across a similar scenario?

Regards,

Kedar