on 09-05-2008 9:57 AM
Hello,
I am having the issue regarding Planned Cost for internal Order.
I have created one internal order for material. I have issued Raw material via Reservation through movement type 261 and received the material as FERT by movement type 932. My settlement rule is created as Cost Center.
I ran overhead calculation for Internal order via KGI2. Costs are also calculated which can be seen in KO02 > Extras > Cost Analysis.
I can see the actual cost but can not see the planned cost. How i can derive the planned cost for internal order?
Regards,
Jigar
Hi Jigar, You can use either ECP or unit costing to bring in planning figures in the Internal Order. Trust this answers to your query!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
After creation of the order, you can plan the order wise with cost element wise separately or overal planning. then you are able to see the planning and actual.
Regards
madhav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.