on 09-05-2008 9:49 AM
Dear All PP Gurus,
Can you please tell me the soln for this issue as below :-
We would like to activate version handling for BOMs . Is there anything else that version handling can handle besides BOMs. (Bill Of Material)?????????
Thanks,
narayan
Dear Narayan Patil,
Revision Level's can be used either processing a Material master record or a BOM.
Revision Levels
Use
A revision level identifies a specific change status of a material with reference to a change number. It is used, for example, to identify changes affecting other areas such as Production.
Integration
You generally assign a revision level when processing a material BOM (bill of material created with reference to a material master record). However, you can also assign a revision level when processing a material master record.
Activities
You can display a revision level assigned to a material by choosing Display revision level on a departmental data screen in a material master record.
For more information on revision levels, see Revision Level in the SAP library documentation Engineering Change Management (LO-ECH).
Check the following link to enhance more on Revision Level.
[Revision Level|http://help.sap.com/saphelp_erp60_sp/helpdata/en/d8/73200e4b7511d1894b0000e8323c4f/frameset.htm]
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.