on 09-05-2008 7:58 AM
Hi All,
I am using SAP R/3 4.6B with SQL DB
SQL Server 2000
In DB13 tcode
there is 1 unknown act planned in DB calendar on Thursday of every week
and this unknown act give every time same error msg.
Please help me for this problem.
Regards,
Saket Bhandare
INDIA
This is the detailed error message
Internal error: unknown action
Message no. S1 426
Diagnosis
The system detected a planning with an action for which it could not
find a description entry in the table SDBAC. Maybe the planning was
entered with an earlier version of the calendar and the corresponding
action is no longer supported.
System Response
Plannings with unknown action types may not be changed.
Procedure
Report this problem to SAP.
Hi,
Not sure about the 4.6B version but there was a know error in the ecc6.0 version after applying the basis support package 11, That the old dba calender scheduled periodic jobs are cancelled they need to be rescheduled. Have you applied any basis patches in the recent past?.
Just try delelting the job and schedule the job again.
Regards,
Vamshi.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Vamshi,
This unknown act is already predefined by some one who was working earlier and even i am not able to find what this act means what planning was defined.
when i used DB13 t-code it shows DBA calender and every Thursday "18:00 PM unknown act"
and even i didn't found any log for this unknown act.
Regards,
Saket Bhadnare