Dear gurus,

I have one query regarding sales order link to MRP run.

I had created sales order by VA01 & also independent requirement in MD61.

Both are acknowledged in MRP run.I know the requirement in MD61 transferred for MRP run(MD02/MDBT/MD01).

But my question is how sales order requirement considered in MRP run i.e. link to MRP run.Is there any customization?

Pl.suggest the same...

Rg,

Tushar

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thnax Brahmankar.....

Former Member
0 Kudos

Dear sir,

We have maintained strategy group 11(Make-to-stock prod./gross reqmts plng) with reqm. types

KSL & BSF and we have REM.

This means "KSL" responsible for transfer of sales order to MRP run?

rg

Tushar

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

Strategy 11 :-

Sales Order creation - no impact.

BSF Gross planned independent requirements

KSL Sale from stock without independent

Requirement reduction

Goods Receipt - minus the quantity for the oldest planned independent in demand management. For e.g. if PIR is 100 and delivery 90, PIR becomes 10 (withdrawal 90).

Delivery - no impact as delivery is issue from sales order.

Hope clear to you.

Regards,

R.Brahmankar

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

In MTO scenario with Planning strategy group 20 in material master .

After sales order is created, Run MRP , then planned order will be created.

You can then convert planned order to production order. Then this production order has a definite link with sales order.

This link is done through planning strategy which contain customer requirement and pp requirement also maintain under requirement class.