HI,

In split valuation,after processing we unable to change moving average price by MM02.Is it possible to change by table level.If so any transaction available..

Thnks & Regards

Sumathi.S

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi,

Use MR21 to change the MAP..

If stock exists, MR21 will trigger a Financial entry

Inventory account and adjustment accounts gets an entry

Regards

Merwyn

Former Member
0 Kudos

Hi,

Once the split valuation is active you cannot change material,

you have to stock out for that material then only you can change the price for that material.

Regards

Ravi shankar.

deiva
Active Contributor
0 Kudos

Hai,

Use TCode MR21 - To change the materail master prices.

former_member192897
Active Contributor
0 Kudos

You cannot Change Price in Material Master Change MM02 for any Cause. Use MR21 Price Change for Changing the Price of Material Master.

Regards,

Ashok

former_member335885
Active Contributor
0 Kudos

Hi,

Once the material is been created with respect to price control V or S. then you cannot change the price through MM02.

You have to use transaction MR21 to change the price of the material.

Thanks & Regards,