on 09-05-2008 5:55 AM
Hi SAP Guys,
I want to compare delivery date and actual PGI date. In likp having so many dates which date should I compare with Actual Pgi date. My requirement is identify the back dated PGI and delay PGI. Here I have seen created on date what the use of this date. Please guide me above issue.
Regards
Venkey
Hi there,
Actual GI date is LIKP-WADAT_IST.
Delivery date is LIKP-LFDAT.
It is not necesary that planned & actual GI date should be same. Coz basing on the replenishment date, item may be available earlier sothat material is processed earlier to planned dates.
Regards,
Sivanand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Venkey
You can Compare these two fields
- Document date : LIKP / BLDAT
- Actual GI Date : LIKP / WADAT_IST
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi there,
Created date is the date on which the delivery is created.
Delivery date is the confirmed delivery date that is porposed after the availability check. It is same as delivery date at item level in SO.
Actual GI date is the date on which GI is done. It is updated after PGI is done. Planned GI date is updated when delivery is created.
Regards,
Sivanand
Actual PGI date field is WADAT_IST in LIKP table.
Regards,
GSL.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.