Lot sizing procedure requirement in REM MTO scenario.

Hi PP Gurus,

The requirement is to get no. of planned orders taking 125kg as fixed quantity. Actually Client wants to give unique batch no. to each planned order though their daily Production quantity is fixed if they get order (that's why we prefer REM).

We know, it is possible in Discrete Manufacturing environment by taking appropriate MRP type with Lot size FX and giving proper lot. After taking MRP run system will create that much Planned order depending on Fixed Lot that we have given in Materials master of that material. But is it possible in Repetitive Manufacturing environment?

We took MRP type PD, Strategy Grp 20 with Fixed lot size 125, REM profile 0002 (standard) with Rate routing and Materials BOM combination in Production Version. Everything required for REM maintained properly. We already checked SAP IDES, there is no such scenario.

Please suggest the best possible options and make your prompt comments.

Thanks & Regards,

Abu Arbab