Cross Docking in SAP R/3 ECC 6.0

Folks,

I'm struggling to make 2-step w/ planned cross docking work. Basically, unable to connect the planned with the candidate document.

Here is the scenario:

1. (Candidate) Outbound delivery created with a delivery date / time of 09/04/08 - 10:00 (No TO initiated)

2. (Planned) Inbound delivery created with a delivery date / time of 09/04/08 - 12:00 (No TO initiated)

The system invokes different messages based on the following config. settings: (These messages occur when I right click on the inbound delivery and select "plan cross docking")

Setting 1:

Planning time: 1 D

Default Release: 1D

Def Latest Release: -

Message: No inbound documents have been selected for planning

Setting 2:

Planning time: 1 D

Default Release: 1D

Def Latest Release: 1D

Message: Time ref. 09/04/2008 10:00:00 of plan.doc. xxxxxxxxx does not match cand.documents time refs

BTW, it's a simple setup WITHOUT transportation, yard management, HUM or SUT.

Thanks in advance for your valuable comments!!