Hi,I have a requirment for following purpose.
I have to assign a project for Resource-Related Billing and save Billing Request.Please suggets me possible steps?
Regards
ricky
Hi,
You must have created sales order for the billing. For RRB,
in sales order item , you have to assign WBS element in Account Assignment tab and DIP Profile in Sales B tab.
DIP profile can be configured thru Transaction ODP1 as per your business requirement.
You can create RRB document through DP90/DP91.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amit,
One question is in my mind. Is it really required to do the resource related billing using DIP profile? As per my knowledge, if we are using DIP profile then only easy cost planning option has to be used.
Instead why cant use automatic/network costing and by using milestone billing, a resource related billing is generated?
Thanks
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.