Cost object problem with current date and future date

Hi everybody,

I have an issue on Costing object

While creating PO w.r.t. pur requistion with current date i.e., 04.09.2008 system able to post it. But same PO with future date i.e., 04.09.2009 system will not able to post and threws error message like

"Account 1005001 requires an assignment to a CO object"

Why system is not asking an assignement to a CO object if we give current date in PO and why system is asking assignment to a CO object if give future date in PO?

Cost element : 1005001

Analysis periods : 01.01.2008 to 31.12.2008

01.01.2009 to 31.12.9999

Looking forward your valuable thoughts/ideas

thanks

anifi

Former Member

Helpful Answer