Actual cost to be extracted from the project

Former Member
0 Kudos

Dear all,

We are developing one enhancement in which extraction of the actual cost and planned cost from the project is involved in Project system.

Using RPSCO table i could be able to extract the planned cost but i could not be able to extract the actual cost. Kindly suggest the solution.

Regards,

sudhir

4 REPLIES 4

Former Member
0 Kudos

Hi Sudhir,

please try selecting by WRTTP = '04' (that's real costs). '01' are planned costs.

I hope it helps. Kind regards,

Alvaro

Former Member
0 Kudos

Dear Alvaro,

I have already tried this option and put in WRTTP the value type as 4 but still i could not be able to extract the actual cost.

Kindly suggest.

Former Member
0 Kudos

RESOLVED

0 Kudos

Hello,

How did you resolve this?