in BOM one assembly is externally procured but i have mentioned raw material needed for the same.

when i run MRP i should get PR for only assembly not for raw material needed for it.it is not suggested to block material for procurement.

roc

Accepted Solutions (1)

Accepted Solutions (1)

pankaj_singh9
Active Contributor
0 Kudos

Hi,

For Raw Materials of Assembly, maintain MRP Type as ND (No Planning) in MRP 1 view of Material Master and for Assembly keep PD. And then run MRP, it will generate requirement for Assembly only not for Raw Materials.

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Based on the Material master data system will trigger for Planning.

Without changing the master data it is not possible. You need to put the ND mrp type in the material master for that Raw materials inorder to stop the requirement for that raw materials.

If the Assembly it self is procured externally then what is the need of the BOM for that Assembly. As you are not procuring any raw materials related to that Assembly.

If you really need the BOM then instead of maintaining the Production BOM maintain it as Engineering BOM so that you are aware of the BOM with Assembly and raw materials.

rgds

Chidanand

Former Member
0 Kudos

Hi

Plz....

ROC

Former Member
0 Kudos

thanx pankaj

other than changing master record ,is it possible,,,,,,,,,?

roc