Hi,
Is there best standard method to put settlement rule and assign investment management which have a lot of WBS structure...rather than assign one by one?
Cheers,
Nies
Hi Nies,
You can maintain investment profile and settlement profile in project profile using the T-Code OPSA in controlling tab page. This will be defaulted to all the WBS elements.
Hope this will be useful to you.
Regards,
Edited by: Balakrishnan Munuswamy on Sep 4, 2008 6:08 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The issue is i need to assign to alot wbs in the same project..
For example...
WBS level1
WBS level2
WBS level 3 (assigned IM)
WBS level 3 (assigned IM)
WBS level 3 (assigned IM)
Could you please advise the best way to put investment id (i use character) to each WBS level 3, rather than manual.
Cheers,
Nies
Dear,
There is procedure for the collective generation of setelment rule .
CJB2 - Individual Processing
CJB1 - Collective Processing
In CJB1 you have to create varrient and then you can generate the sattelment rule for meany WBSE .
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.