contract or scheduling agreement

Hi friends,

Given a scenario,

how can i decide , whether to use contract or scheduling Agreement.

after reading sap help, i am confused, it gave little difference between both.

Can some one please tell me on what factor or basis , i should decide on Contract or SA.

Thanks.

Former Member
replied

Hi Vinay,

There are few differences which shd be taken into mind while you for one among outline agreements:

1. Whether the schedule is fixed or not ...or may extend...if gonna extend then its better to use schedule agreement because here the period will be qixed...but not qty and schedule....

While in Contract, there are two options value as well as qty contract....while can be made more precise by using the doc. type like, m and w...

2. As compared to contract in schedule agreement, there is no need to make new del. schedule for each new req. you can add your new req. in the available del schedule...

While in contract, for each new requirement you need to create new release order every time....which is time consuming alongs with n number of doc. generated in your system for the same req.

Hope it helps

Regards

Priyanka.P

AWARD IF HELPFULL