on 09-03-2008 2:01 PM
Hi ,
While transferring project stock to sales order stock in MB1B system with movment type 413 Q gives the following error.
Valuated project stock not allowed with customer stock.
Message no. KI346
Diagnosis
The entered WBS element E-00000108 manages a valuated project stock. At the same time, a sales order stock is managed on the sales order item. This combination is not allowed since different valuation methods within a project are not allowed.
System Response
Processing is not continued.
Procedure
Enter a WBS element that does not manage a project stock or only a nonvaluated project stock, or change the inventory management for your sales order item in the valuation class.
Pl suggest.
Rgds
As the error message says, you can not mix Valuated Project Stock and Sales Order stock. You need to find out why do you need to transfer project stock to sales order stock. What is the need?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.