on 09-03-2008 1:33 PM
Hi All,
I am using Investment Management. I would like to distribute budget in IM52. but in IM52 it shows the WBS code not the wbs description, how to make it change to description ?
Please help.
Cheers,
Nies
Dear,
You can change with CJ22.
Please also check CJ20N.
Regards,
Mahesh Wagh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nies,
In the configuration of the Investment program type you can define if you want to represent the positions and measures (e.g. projects) by ID or text.
Please follow the path in the customizing:
SPRO>Investment Management>Investment Programs>Master Data>Define Program types
There is a field called "Repr.form" (Represent. of cap. inv. prog. position in graphic hierarchy) that determines if the ID or text will be displayed.
For example, if you set the value for 3 the investment program position will be represented by the code and the measure (in your case the WBS element) by description.
Hope it helps,
User | Count |
---|---|
97 | |
10 | |
10 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.