actual overhead costs calculation

Hi,

i've got a probleme with actual overhead costs calculation in PS.

I plan costs on activity elements for activity types. i've got costing sheets and costing variants for actual and planned values.

when i do ctrl+f10, the planned values are calculated for the activity type and its associated overhead costs. (no need to launch t-code cj46)

then i do enter times in cat2, transfer them to ps through cat5, the hours are valudated in the activty element but not the overhead.

i always have to use cj44 to transfer actual overhead to project.

is this t-code a compulsory step to transfer overhead costs to PS? or is my costing variant not properly customized?

regards

xavier